It is good to see the development of the RFI process that works with the Submittals process. It would be GREAT to complete this effort and complete the loop on all the typical industry standard methods for changing the scope of work (and related drawings, tasks, sketches, communications, etc…).
For example the following methodologies need to be added:
1. Addenda
2. Change Requests (or Proposal Requests)
3. Change Orders
4. Clarifications (or Architects Supplemental Instructions)
5. Field Orders (directed changes without agreement on cost or schedule)
All of the above are industry standard ways of modifying the scope and related drawings and specifications beyond the RFI process. The underlying flow of information and issue tracking is remarkably similar to both submittals and RFI’s. It would be phenomenal to have the same tracking, addressing and tasking flow as the submittal and RFI process added to Newforma.