How to Re-path a project when the project files have changed File Server locations

1.If you are not already there, open the Project Center Administration activity center by clicking Project Center Administration from the Tasks panel of the My Project Center activity center, or from the Activities list.

2.From the Projects tab, click Re-path Projects from the Tasks panel to open the Re-path Project Folders dialog box.

3.In step 1, enter the full path to the parent folder of the original project folder location in the Original Location field, then enter the full path to the folder’s new location in the New Location field. Click the image button to locate the folders if necessary. Click Next.

image

4.In step 2, mark the checkboxes of the projects whose project folders were moved to the new network location. Click Finish to notify and update the Project Center Server about the moved project folders.

image

5.When the process is complete, the following screen appears showing the status of the process.  Click Open Log if you want to view and save the log file.